1

Design of 36 MLD water supply scheme to Alumina Refinery of M/s Vedanta Aluminium Ltd. at Lanjigarh, Odisha.

CLIENT: SIMPLEX INFRASTRUCTURE LTD.

CONTACT: MR. A.K. CHATTERJEE

DESIGNATION: DIRECTOR (TECH.)

Field Survey-For 70Km of pipeline alignment, River cross section and river contours at Redial Well location, Grid Survey for Radial well and Intermediate Pump House, Substation.

Hydraulic Design: Pumping out test, Radial well Rising main, Sump, Earthen Reservoir etc.

Structural Design: Radial well ID- 8m ID and OD- 10m, by sinking method 15.6m below RBL of total height 24.8m with, circular Over Head Pump House of ID- 8m. Steel approach bridge with foundation and piers in RCC of width 3.6m and length 115m. Intermediate Sump of Capacity 30ML and Pump house, switchyard and substation approach ramp all pipeline structures.

Radials: 300mm dia. steel radials pushed at 10m below RBL. Total 16nos of 565m length.

Rising Main: 700mm NB MS pipe of length 63.76 Km in two stages of 34.86 Km and 28.9Km with max. field test pressure of 297m and 265m respectively.

Pumping Machinery: 4 VT pumps with design head of 187m installed on Radial well and 4 Centrifugal pumps with design head of 178m installed on Intermediate pump house, each pump with duty discharge of 139LPS.

Substation: 33/6.6KV 1.7MVA x 2 and 1.6MVA x 2 Transformers substations including all electrical system and switchgears switchgears.

Earthen Reservoir: Capacity 210ML with HDPE film with CC lining from inside.

Utilities like staff quarters, storm drainage, illumination, internal electrification etc. complete.

Completed in 2006.

2

Detail Study and Designing required for revamping of existing Raw Water system with withdrawal capacity of 30 to 40 MLD water to be delivered to Alumina Refinery plant of Vedanta Aluminium Ltd. at Lanjigarh, Odisha

CLIENT: VEDANTA LTD.

CONTACT: MR. P. KUMAR DESIGNATION: HEAD INFRASTRUCTURE

Field Survey-For 2.5Km of pipeline alignment, River cross section at Radial Well location, Grid Survey for Radial well and Substation.

Hydraulic Design: Pumping out test, Radial well Rising main,

Structural Design: Radial well ID- 16m ID, by sinking method 13.3m below RBL of total height 26.3m with, Rectangular Over Head Pump House of 19.2(L)x17.3(W)x11.65(H)m. RCC approach bridge with foundation and piers in RCC of width 6.5m and length 75m. Switchyard and substation approach ramp all pipe line structures.

Radials: 300mm dia steel radials pushed at 5.4m below RBL. Total 29nos of 1217m length. Rising Main: 700mm NB MS pipe of length 2.5 Km with max. field test pressure of 297m and 265m respectively.

Pumping Machinery: 4 VT pumps with design head of 225m installed on Radial well each pump with duty discharge of 185.33LPS. Substation: 33/6.9KV 2.5MVA x 2 Transformers substations including all electrical system and switchgears.

Utilities like illumination, internal electrification etc. complete.

DPR

Completed in Year 2018 & commisioned in 2024

3

Detailed design consultancy services for Upgradation of Nanded-Kinwat-Mahur-Arni Road section from Sarsam Budruk to Kothari for Sunil Hi Tech Engineers Ltd. & Varaha Infra Ltd.(JV)

CLIENT: Sunil HiTech Engineers Ltd.

CONTACT: MR. Sunil Gutte

DESIGNATION: Managing Director

Detail Design work involving Field Survey, Geo Technical Investigation. Preparation of Plan and Section of road profile. Detail design of Flexible pavement and Rigid payment. Design of Culverts, Bridges. Etc. complete.

Design work completed.

4

Detailed Design and Drawings for Intake Well of 23MLD LAHCHURA & KASHIPURA Scheme, Uttar Pradesh.

CLIENT : JMC PROJECTS (INDIA) LIMITED

Calculation of H.F.L. and scour depth for finalizing the height of Jack Well/Intake Well and its foundation depth respectively. Preparation of all electromechanical design and drawings for proposed Jack Well cum Intake well. Preparation of Structural Design of Intake Well. Detailed design and drawing for Coffer Dam and other enabling structure for construction of Intake Well and Approach bridge along with its BOQ.

Preparation of GAD and structural design & drawing for Approach Bridge from Intake Well. Preparation of layout and Hydraulic flow diagram along with Hydraulic process calculation. Drawing with BOQ for WTP, CWR I/C drawing with SCADA, instrumentation, Control.

Detailed Engineering & Design work completed.

Year 2020-21

5

Consultancy for preparation of Detailed Project Report (DPR) and Detailed Engineering for 2111 Revenue villages in four district (Amethi, Ambedkar Nagar, Sant Ravidas Nagar & Jaunpur) of UPJJM with Technical support.

CLIENT : WESPUN ENTERPRISES LIMITED,

Contact – MR.V BALASUBRAMANIAM

DESIGNATION – HEAD ENGINEERING

TEL: - +91 2266136000

Preparation of DPR & Technical Specification for Mechanical and Electrical equipment. GAD for Pump House and ESR Layout. Specifications for Water Treatment Plant. Detailed Engineering for OHT. Schematic Diagram for SCADA. Operation and Control Philosophy. Technical Support during execution of project.

Detailed Engineering & Design work completed.

Year 2022 -23

6

Consultancy Services for Preparation of Surge analysis report of As Built data provided by KPTL team for Rising Main 3, 4 and 5– Narmada - Jhabua Irrigation Project.

CLIENT – JMC _ KALPTARU POWER TRANSMISSION LTD, MUMBAI.

Contact: MR. MOTILAL NADIMETLA

Pipe elevation Profile, Results and graphs without surge protection. Results and graphs with surge protection. Conclusion and recommendations. L‐section with Surge equipment locations as per the department format.

Rising Main: RM‐3 from PS‐3 to DC‐1: 2450 mm dia 20.22 kM RM‐4 from PS‐3 to PS 4: 2165 mm dia 15.620 kM RM‐5 from PS‐3 to DC‐2: 2165 mm dia 15.07kM Length

Detailed Engineering & Design work completed.